PPP Law in Infrastructure Projects: What investors need to know? - Part 1

Trường Lăng
Trường Lăng, founder and 15-year director of Viettonkin, guides the company's strategic direction, makes top-level decisions, and represents the firm in key business negotiations. With over 20 years of consulting experience in Belgium and Southeast Asia, including 15 years specializing in FDI projects, he has established himself as a top expert who helps clients across industries expand their businesses. His deep knowledge of risk management and business operations, combined with his proven track record of successful consultation projects, makes him a valuable partner for investors seeking quality consulting services.

According to government official statistics from 2019 the line ministries, agencies and provinces have signed and implemented 336 PPP projects, with a total investment capital of VND 1,609,335 billion (about US$ 70 billion). The dominant share of PPPs is in the field of transportation (220 projects); resettlement housing, dormitories, etc. (32 projects); office buildings (20 projects); energy (18 projects); as well as water supply, sewerage, environment (18 projects).

On June 18, 2020, the National Assembly of Vietnam passed the long-awaited Law on Public-Private Partnership (PPP Law), and aims to attract more private investment to the development of Vietnam’s infrastructure. The PPP Law took effect from January 1, 2021, and replace the previously issued PPP regulations under Decree 63/2018/ND-CP of May 4, 2018 (Decree 63). Some of the key changes under the Law, some positive and some less so, with respect to making the PPP framework more appealing to private sector developers, investors, and lenders.

Sector eligible for PPP projects

The PPP Law has narrowed the sectors eligible for PPP projects (Permitted Sectors). The regulated sectors are now as follows: 

(i) transportation;

(ii) power plants and power transmission lines, except hydropower plants and monopoly cases of the State under the Law on Electricity;

(iii) irrigation works, clean water supply, water drainage and wastewater treatment, and waste treatment;

(iv) healthcare, education and training; and,

(v) information technology infrastructure.

Investment models

In line with international practice, the PPP Law no longer recognizes the Build-Transfer model (BT) of PPP investment under which investors could recover their investment by exchanging BT projects for land use rights to be used for other projects. All BT projects that have not been approved and issued with an approval in-principle of the investment plan (the AIP) must be stopped from August 15, 2020, and no new BT project will be considered going forward. This removal would have an impact on several property projects linked with a BT project.

As a result, there are now seven types of permitted PPP investment models: Build-Operate-Transfer (BOT), Build-Transfer-Operate (BTO),  Build-Own-Operate (BOO), Operations and Maintenance (O&M), Build-Transfer-Lease (BTL), Build-Lease-Transfer (BLT), and mixed contracts combining (a) BOT, BTO, BOO or O&M and (b) BTL or BLT.

In terms of primary contract types, BOT and BT forms are dominant, comprising over 95 percent of PPPs. BOO and BLT are far less common.  In discussing PPP contract types with a large domestic commercial bank, it was noted that they were only interested in financing BT projects, where there was land as collateral.

tron le MjYzuyjPUFo unsplash

Investment Capital

The PPP Law imposes the following minimum investment capital requirements for PPP projects, with the Ministry of Planning and Investment noting in forums the preference for larger-scale projects:

(i) VND 100 billion (approximately USD 4.35 million) for PPP projects in healthcare, education, and training;

(ii) VND 200 billion (approximately USD 8.7 million) in other Permitted Sectors, but VND 100 billion if the projects are located in areas with difficult socio-economic conditions or extremely difficult socio-economic conditions (as defined in the Investment Law); and,

(iii) no minimum investment capital is required for PPP projects implemented under Operations and Maintenance (O&M) contracts.

Capital Participation in PPP project

As with Decree 63, Government support can come in many forms and the PPP Law sets out the following permitted uses for state capital contribution to a PPP project: (there are 6 in total) with the first two:

(i) support for the construction of works and infrastructure systems for a PPP project;

(ii) payment for land clearance, compensation and resettlement, and support of the construction of temporary works;

State capital contribution is limited to no more than 50 percent of the total investment capital for permitted uses (i) and (ii) above. For projects with multiple component projects, including PPP component projects, the state capital contribution ratio will be determined on the total investment of such components.

Under the PPP Law, the equity capital contribution of the private investors in a PPP project must be at least 15 percent of total investment capital. Any capital contribution from the State is not counted toward investment capital for the purpose of determining the equity capital to be contributed by private investors. These requirements are more relaxed than those under Decree 63 which required an equity capital contribution of at least 20 percent of total investment capital for PPP projects with investment capital of up to VND 1.5 trillion (USD 64.7 million equivalent) plus at least 10 percent of the portion of any investment capital exceeding VND 1.5 trillion.

Unlike its predecessor, the PPP Law provides a timeframe for capital contribution to a project company. The investor(s) and the project company will be responsible for contributing equity and raising loans and other capital sources to implement the PPP project within 12 months from the signing of the PPP contract. This period can be extended to a maximum of 18 months for projects with an AIP issued by the National Assembly or Prime Minister.  However, the PPP Law is still silent on whether the required equity capital can be contributed in stages or in an agreed debt to equity ratio with loans over the construction period. This aspect is expected to be addressed in the forthcoming implementation and guiding regulations on the PPP Law.

to be continued

Unlock Vietnam's Market: Download Our Comprehensive FDI eBook Now!

Vietnam is emerging as a prime destination for foreign direct investment (FDI), driven by rapid economic growth, favorable government policies, and an investor-friendly business environment. This eBook provides a deep dive into Vietnam’s economic landscape, highlighting key industries such as manufacturing, real estate, and digital banking that attract FDI. It also explores the government’s proactive measures to streamline investment procedures, improve infrastructure, and offer tax incentives for foreign enterprises. Additionally, it covers crucial insights into market entry strategies, regulatory requirements, and socio-cultural factors that influence business success in Vietnam.


Download the eBook now to gain expert insights into successfully navigating Vietnam’s dynamic investment landscape!

Download EBOOK
Unlock Vietnam's Market: Download Our Comprehensive FDI eBook Now!

Vietnam is emerging as a prime destination for foreign direct investment (FDI), driven by rapid economic growth, favorable government policies, and an investor-friendly business environment. This eBook provides a deep dive into Vietnam’s economic landscape, highlighting key industries such as manufacturing, real estate, and digital banking that attract FDI. It also explores the government’s proactive measures to streamline investment procedures, improve infrastructure, and offer tax incentives for foreign enterprises. Additionally, it covers crucial insights into market entry strategies, regulatory requirements, and socio-cultural factors that influence business success in Vietnam.


Download the eBook now to gain expert insights into successfully navigating Vietnam’s dynamic investment landscape!

Download E-Book

About Us

Founded in 2009, Viettonkin Consulting is a multi-disciplinary group of consulting firms headquartered in Hanoi, Vietnam with offices in Ho Chi Minh City, Jakarta, Bangkok, Singapore, and Hong Kong and a strong presence through strategic alliances throughout Southeast Asia. Our firm’s guiding mission is aimed towards facilitating intra-ASEAN investments and connecting investors in Southeast Asia with the rest of the world, thus promoting international business relationships and strengthening inter-nation connections.
Contact
Email: 
info@viettonkin.com.vn
Phone Number: 
+84 977093166
Support
FAQ
Subscribe to our insights to look at the critical issue that your business is facing and stay ahead of the competition in a rapidly changing world.
Subscription Form
img linkedin
Viettonkin Consulting Logo © 2025 - Viettonkin JSC